The Meeting and Teleconference Summaries contains basic information about this project and a summary paragraph from each meeting or teleconference held for this project.


Contractor: The Boeing Company (formerly BISDS), Northrop Grumman

Potential Programs/Owners: AV-8B, C-5, C-17, C-130, C-141, EA6-B, E-2/C-2, F/A-18 C/D E/F (production), F-5, F-15, F-16, F117, H-1, H-46, H-47, H-53, H-60 (depot and intermediate level), H-64, H-65 Orbiter, P-3

Material(s) Targeted for Reduction/Elimination: High-VOCs

Phase(s) in Methodology: I, Identification



Milestones and Prior Decisions:

  • April 2003 - The participants agreed, via email, to suspend project efforts until a more viable alternative was developed.
  • April 19, 2001 - The participants, at an early customer interface meeting, agreed to pursue a Low-VOC Adhesive Bonding Primer JG-PP project.

Date of Last Meeting/Teleconference: January 10, 2002
Next Scheduled Meeting/Teleconference: To be determined

Meeting/Teleconference Summaries:

If you would like to review the full version of the minutes, please contact the project point of contact, Lorraine Wass .

On January 10, 2002, representatives from the Navy, Air Force, Army, NASA, and OEMs participated in a teleconference with representatives from the JG-PP WG (formerly known as JASPPA). The primary objective of the meeting was to discuss suspending this project pending qualification of additional alternative adhesive bonding primers.

On October 4, 2001, representatives from the Navy, Air Force, and OEMs participated in a teleconference with representatives from the JG-PP WG (formerly known as JASPPA). The primary objective of the meeting was to review action items and the draft JTP.

On July 12, 2001, representatives from the Navy, Air Force, and OEMs participated in a teleconference with representatives from the JASPPA. The primary objective of the meeting was to review action items and the draft JTP.

On May 31, 2001, representatives from the Navy, Air Force, and OEMs participated in a teleconference with representatives from the JASPPA. The primary objective of the meeting was to review action items and the draft JTP.

 

Related Topics

Project Matrix and Points of Contact

Current Project Activity

Meeting and Teleconference Summaries

Technology Survey

Potential Alternatives Report

Joint Test Protocol

Joint Test Report

Information Sheet

Project Summary

 

This site last updated December 10, 2009.


Send all questions and comments to jgpp@ctc.com